Project Specifications

Technical Details
Total Area
35,000 m²
Floors
2 floors
Duration
15 months
Budget
R65 million
Key Features
High-bay warehouse storage
Automated conveyor systems
Loading dock facilities (20 bays)
Office and administrative areas
Temperature-controlled sections
Advanced security systems
Solar panel installation
Fire suppression systems

Equipment Used

Professional-grade construction equipment and machinery used in this project

Mobile Crane 100T
Heavy Lifting
Mobile Crane 100T
Lifting capacity: 100 tons
Boom length: 60 meters
Used for: Steel frame erection
Reach: 50 meters
Forklift Fleet
Material Handling
Forklift Fleet
Capacity: 3-5 tons each
Lift height: 6 meters
Used for: Material placement
Fleet size: 8 units

Project Timeline

Detailed timeline showing each phase of the construction process

Foundation & Structure

6 months

Foundation work and steel frame construction

Completed

Building Envelope

4 months

Walls, roofing, and weatherproofing

Completed

Systems Installation

3 months

Mechanical, electrical, and automation systems

Completed

Fit-out & Testing

2 months

Interior fit-out and system commissioning

Completed

Project Gallery

Visual documentation of the construction process and final results

Steel erection
Warehouse interior
Loading docks
Office areas
Completed warehouse
Systems installation

Project Team

Meet the dedicated professionals who brought this project to life

James Wilson

Industrial Project Manager

22+ years

james@ruijieengineer.co.za
+27 11 234 5685

Interested in a Similar Project?

Let's discuss how we can bring your construction vision to life with the same level of excellence.